Supplementing a "lump sum" bid
To supplement a "lump sum" bid, right mouse click on the lump sum amount and choose supplement. Next, enter the supplemental amount. The supplement amount can either be a positive or negative number. A positive amount will be represented by a down-arrow in the lump sum cell and a negative amount will be represented by a down arrow in the lump sum cell.
Related Articles
Entering Lump Sum Bids
To enter a lump sum bid, click on the + Add Subcontractor at the top of the Bid Package Matrix. Add the subcontractor to the Bid Package Matrix. If you are using SmartBid or BuildingConnected, you will be selecting a subcontractor from the list of ...
Adding a Lump Sum markup
To add a Lump Sum markup click on the Totals / Markups option on the Summary Sheet toolbar. Next, right mouse click on any row in the Totals / Markups panel and select Insert New Below or Insert New Above. This will bring up the Add Markup window. In ...
Supplementing Quotes From the Clarification List
When you add clarifications to a bid package, some clarifications may have a dollar impact on a subcontractor’s bid, and some may not. To supplement a phase from a “clarification”, right mouse click in the cell and select the supplement option from ...
● Supplementing bids for missing “item scope”
You can add or cut dollars from a subcontractor's phase quote by using the Supplement option on any cell in the matrix which includes a bid for a bid package phase. To supplement a bid, right mouse click on the bid package phase cell that contains ...
Deleting a Bid Package
Bid Packages can be deleted from the project Summary Sheet. Click on the ellipsis icon to the left of the bid package code you wish to delete. Click on the delete option to remove the bid package from the project. You can also delete a bid package ...