Changing the Subcontractor Order in the Matrix
To change the order of the subcontractors in the matrix, click in the subcontractor name column header, hold the left mouse button down, and drag the column to the desired position.
Related Articles
Changing the Summary Sheet Column Order
To change the order of the columns on the Summary Sheet, click on the column label. Hold down the left mouse button and drag the column to the desired location. BidMatrix will remember this column order then next time you enter the project ...
Viewing/Changing Subcontractor Attributes Displaying in a Bid Package
As you click on subcontractors and any of their bids in the bid package matrix, you can see important information about that subcontractor. The information for each subcontractor displays in the lower right of the Details tab within each bid package ...
Attaching Files to Subcontractor in a Bid Package Matrix
Files can be attached to a subcontractor that has been added to a bid package matrix. To attach a file to the subcontractor in the bid package, right mouse click on the subcontractor name cell. Next, click on the Attach File option. You will be ...
Disconnect a Category Cost From the Subcontractor Matrix Budget
In a situation where you don't want a category cost for a phase to be part of a bid package matrix, you can "disconnect" the category cost from the subcontractor phase budget. For example, you might wish to disconnect category costs from a phase ...
Breaking Out a Category Cost From the Subcontractor Matrix Budget
From time to time, you may want to "breakout" a category cost from a phase budget, so you can enter bids separately for the category cost you've broken out. For example, you might want the subcontractors that are bidding a phase, to give you a bid ...